Segment 3B
Length:
10.0 miles
Project Type:
Toll Road
From:
SH 31
To:
I-20
Initial Section:
2-Lane Undivided
Ultimate Section:
4-Lane Divided
Status:
Completed
Opened: March 2013
Toll 49 Segment 3B was delivered using the design-build development concept. This segment extends from SH 31 north to I-20, a distance of approximately 10.0 miles. CH2M Hill, the design-build developer, was selected in June 2010.
The NET RMA received funding for Toll 49 Segment 3B through a State Infrastructure Bank Loan, and a Toll Equity Loan provided by TxDOT.
Construction took approximately 22 months with Toll 49 Segment 3B opening to traffic as a toll road on March 2013.