PROJECT: Toll 49 Segment 5
Length: 2.5 miles
Responsible Entity: TxDOT
PROJECT TYPE: TOLL ROAD
FROM: FM 756 (Paluxy Road)
TO: SH 110 Near Whitehouse
INITIAL SECTION: 2-Lane Undivided
ULTIMATE SECTION: 4-Lane Divided
OPENING DATE(S): STATUS
Segment 5: June 2012 Construction
Toll 49 SEGMENT 5:
Toll 49 - Segment 5 extends from FM 756 to SH 110 near Whitehouse, a distance of approximately 2.5 miles. This segment was designed by the NET RMA General Engineering Consultant, with 100% plans completed and accepted by TxDOT in January 2008. The NET RMA and TxDOT are now working jointly to arrange financing for construction of Segment 5. Construction on this segment is anticipated to take approximately two (2) years, with Toll 49 - Segment 5 potentially opening to traffic as a Toll Road in June 2012.